  • [RB] Resolved an issue when copying a Requisition and the supplier had been change where all the supplier contact details stay the same as the previous selected supplier.
  • [RB] Resolved an issue with the Approval Route Report missing values for users with Nominal Account Overrides approval values.
  • [RB] Resolved an issue with MRP Requisitions defaulting to the Administrator Account rather than the Route specifically designed for them.
  • [RB] Resolved an issue with Goods Receiving Requisitions where If the user selects a requisition to goods receive, they cannot see the activity that the requisition line was raised against on Stock Item Lines.
  • [RB] Resolved an issue with the Project Phase column on all Requisition reports showing N/A despite the order line being raised to a specific Activity.
  • [RB] Resolved an issue with ad hoc approval routes adding users to the default approval routes.
  • [RB] Resolved an issue with users being able to enter a Document Type against a project that is archived in Project Accounting. Now a pop up will appear on a Submission and Approval (if the Project was archived since the Requisition was raised) to advise it cannot proceed until the Project is changed to an open one or the Project is unarchived in Sage.
  • [RB] Resolved an error appearing when running Expense Nominals Report with no Sage Database specified. A pop up will now appear to advise the user to select a Sage Database.
  • [RB] Resolved an issue with trying to raise/approve a VAT only invoice in Sicon Approvals.

Change in Functionality
  • [RB] Added the Project Phase column to the Outstanding Order Report.