Issues Resolved Important
Important Info

ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v18 FOR THE FIRST TIME

Works Order Processing

  • When using Job Costing and opening a WOP screen for the first time after upgrading, a Job Costing transaction migration will begin.  This will remove all existing transactions for works orders from jobs, and replace them with a single transaction.  From now on, only a single works order transaction will appear on jobs.
  • SiWorksOrderAllocationLine has been removed and replaced with SiconAllocationLine. SiconAllocationLine.ForeignID links to SiWorksOrderLine.SiWorksOrderLineID.  You can now get the picked and allocated quantity from SiWorksOrderLine.
  • SiWorksOrderAllocIssHist has been removed and replaced with SiconWorksOrderLineIssueHistory.  SiconWorksOrderLineIssueHistory.SiWorksOrderLineID links to SiWorksOrderLine.SiWorksOrderLineID.  SiconWorksOrderLineIssueHistory stores information when a works order line is issued and links to the transaction history table by IssueTransactionHistoryID.

Issues Resolved

Works Order Processing

  • Unissue of traceable items will no longer allow users to select less than the required serials, unless the ‘allow part unissue’ setting is enabled
  • Sage transfer stock form will no longer allow users to transfer stock allocated to a works order
  • The back flush process will now post labour and machine time correctly
  • Labour description will now save on first try when adding to a works order
  • Settings ‘Months to display in process screens (each way from today)’ and ‘Enable finished products tab’ can now be enabled on the main settings screen
  • Fix to stop ‘out of memory’ exception appearing when running the Job Costing transaction migration

Material Planning

  • Fix to works order suggestions where lead time was being multiplied by the quantity of the suggestion giving very long lead times.  This may need to be put back at a later date when lead time is changed to be based on economical batch size