Works Order Processing

  • [#17286]: Fixed booking in unconfirmed costs when there are unbooked transactions. The last booking in transaction was sometimes appearing on the works order as negative (the actual posting in stock control and stock history was correct).
  • [#18084] Fix to improve the performance of loading the works order desktop list.
  • [#18079] Fix to ensure we set the ‘BudgetUnitCost’ and ‘BudgetQuantity’ on ‘SiWorksOrderLine’ table when creating a works order. This can lead to an issue when viewing the ‘Works Order’ tab on a ‘Project’ and the ‘Component’ ‘Original Estimate Cost’ remains at 0.
  • [#18342] Fix for getting the correct component warehouse for a sub assembly when it is on the parent and no overrides have been set but the user has specifically selected a warehouse. This keeps the sub assembly finished item warehouse in the same warehouse.
  • [#17422] When using a batch traceable finished item, and the user clicks in the traceable list on the Traceable Items tab on the works order, the batch number was not auto populating.
  • [#11351] Works Order Summary Actuals vs Budgets are now correctly calculated when creating a new Works Order so they match the figures shown elsewhere in the system.
  • [#8603] Works Order Summary ‘Calculate Summary’ now correctly calculates component costs for FIFO items.
  • [#17938] Receiving a sub-contract on a WO with deleted operations will now correctly show the product booking form.
  • [#18073] Fix to ensure the Project controls on a works order are disabled before creation.
  • [#18220] Fix to allow BOM references to differ from the stock item code. Issue where suggestions were not being created in MRP due to this or issues were created when attempting to create the works order. [“Object Reference Error”]
  • [#18243] Removed SQL that was run when updating companies that would incorrectly set the ‘CostValue’ and ‘UnitCostPrice’ of transaction histories to 0 when the ‘TransactionType’ was 24 and the ‘NominalUpdated’ = 0.
  • [#18238] Fix when amending a BOM record. [“Object Reference Error”]
  • [#18265] Manufacturing migration script is now more robust with int to bigint migrations.
  • [#18105] Fix to include the cost of ‘Misc’ items for committed cost Project transactions. Also include Misc items to the ‘Component Issues’ tab on the ‘Works Order’ tab of a Project enquiry.
  • [#18578] Fix for overhead recovery values not being applied to works order lines that are added to a works order.
  • [#18578] Fix to updated the overhead recovery on the SiWorksOrder so that it is per finished quantity. Issue when drilling down into the cost and the overhead amount would incorrectly multiple out per booking.
  • [#11972] Fix to no longer allow areas to be deleted if they are currently in use. Report these back to the user.

Material Resource Planning

  • [#18348] The Suggested Stock Transfer settings and tab are now disabled for Distribution MRP as they’re not used.
  • [#16521] Users of Distribution MRP can now access ‘Purchase Requisitions In Approvals’.
  • [#13511] Fix for extra suggestions being made for stock items that have not been selected if the user picks to run MRP by a specific stock item.
  • [#11703] Fix to deploy the config file when installing Manufacturing for the stand alone MRP exe. This deploys to the ‘Sage/Custom/Sicon/MRP’ folder to handle the Log4Net error that gets produced on startup. [“log4net:ERROR Failed to find configuration section ‘log4net’ in the application’s .config file. Check your .config file for the <log4net> and <configSections> elements…”]
  • [#18397] [#18398] Fix when creating user suggested POs or combining suggested POs in MRP. [“Unable to case object of type ‘Sicon.Sage200.MaterialPlanning.Objects.SiMRPSuggestedPOLIne’ to type ‘Sicon.Sage200.MaterialPlanning.Objects.SiMRPPOSuggestedView'”]

Kitting

  • [#16415] Fix to not allow the parent kit item to be added as a component of a kit as this would cause a circular reference.

Change in Functionality

Material Resource Planning

  • [#9345] Works Order Stock Settings Import (MRP) upgraded to use new interface inline with Works Order Import. Default Supplier Lead Time for Sage/MRP can now be explicitly set.