221.0.88
Issues ResolvedIssues Resolved
Works Order Processing
- [#11295] Fix for settings being incorrectly disabled based on the compatibility with other works order settings being enabled. ‘Use warehouse hierarchy’ and ‘Show allocations screen to split allocations across multiple warehouses’.
- [#12570] Prevent phantom BOMs from being available as finished items on the dropdown when creating a new works orders.
- [#13438] Improved error handling from ‘Generate SO From WO’ screen so it no longer crashes out of sage.
- [#13664] When adding Subcontracts to a Works Order, only the Subcontract Operations with associated supplier will be listed for selection.
- [#13623] Fix error when closing a BOM Operation when maintaining an operation from Bill of Materials List and the Operations Register. [“Object Reference Error”]
Material Resource Planning
- [#13258] Fix to correctly display on the ‘Suggested Works Order’ tab the ‘Base UOM’ and ‘Base UOM Quantity’ if there is a ‘Production UOM’ set against a stock item.
- [#13628] Fix for a sorting issue on the ‘Suggested Works Order’ tab when sorting by the item code. [“Failed to compare two elements in the array”]
- [#13653] Fixed an issue when running MRP and if a suggestion was to be processed before the out movement a further check to make sure the movement is processed after the earliest date it can arrive, otherwise extra suggestions could be made unnecessarily.
Date applied: March 12, 2025