221.0.77
Issues ResolvedIssues Resolved
Works Order Processing
- Fix backflush add stock button not adding new stock when warehouse hierarchy is enabled.
- Works orders no longer recalculates costing for non labour operations from the timesheet save on the labour tab.
- Fix when adding a new finished item to a works order and adding materials with a sub assembly and this would cause sage to hang.
- Fix to display the correct ‘Labour’ and ‘Machine’ costs on the ‘WIP summary’ report dependant upon labour/machine costing settings.
Material Resource Planning
- Fix for ‘Direct PO’ suggestions being missed when running MRP.
- Fix for standalone MRP displaying the company id of 0 when it has connected to a company.
Date applied: October 2, 2024