ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v22.1 FOR THE FIRST TIME.  THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.

TRANSACTION HISTORY FOR UNCONFIRMED COSTS WHERE THE NOMINAL HAS NOT BEEN UPDATED WILL HAVE THE COST VALUE REDUCED TO 0. THIS IS TO FIX INCORRECT VALUES BEING SHOWN ON THE RETROSPECTIVE STOCK VALUATION REPORT.


New Features

Works Order Processing

  • References to WAP renamed to Approvals
  • Setting added to set a default if we don’t show the prompt to update works order due date on sales order promised date.
  • When adding operations to a works order, the BOM operation resource efficiency will be used to calculate estimated length.

Material Resource Planning

  • References to WAP renamed to Approvals

Issues Resolved

Works Order Processing

    • Fix to stop error occurring when there is a variance value when scrapping.
    • Fix to use working days for delivery buffer days when generating works orders from sales orders.
    • Fix to copying quotes that contain estimates in SOP.
    • Fix to calculate the correct estimated cost for sub assembly lines that have been part issued and don’t have a sub assembly associated.
    • Fix to add nominal code to non stock items when creating the purchase order from the works order.
    • Fix to new feature to split purchase orders by supplier, and show each stock item for each warehouse when group lines of the same item has been checked.
    • Fix to not set use by date against traceable items where the stock item doesn’t use use by dates.
    • Fix to show the correct quantity remaining when receiving the final part of a preallocation that is less than the total of the booked quantity but that quantity is less than the total preallocated quantity.
    • Fix when allocating a works order to allow allocations to be split across multiple warehouses.
    • Fix to keep the child nodes of a works order expanded when booking works orders.
    • Fix to project integration to handle non stock items.
    • Fix to show the non stock setting nominal header in the works order settings screen.
    • Fix to stop error when getting bin from warehouse hierarchy using the data context when updating from BOM.
    • Fix to stop error when using update from BOM on multiple works orders.
    • Fix to remove duplicate lines from merge.

Material Resource Planning

  • Fix to include quarantined locations to the warehouse multi select to be selected on the future stock movements screen
  • Fix to group stock level option movements correctly.
  • Fix to create the stock level option using the correct date when the stock is below the stock level option to begin with but goes back above the stock level option quantity before the earliest date the stock could be received.
  • Fix to show the correct purchasing unit of measure and stop showing units that do not have a stock item unit.

Kitting

  • Fix for when creating a new sales order line that has a kit on without stock. If the user then selects to build the kit this will allocate the new kit to the line and then when the user would save this new line it would get allocated twice incorrectly