ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v22.1 FOR THE FIRST TIME.  THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.

TRANSACTION HISTORY FOR UNCONFIRMED COSTS WHERE THE NOMINAL HAS NOT BEEN UPDATED WILL HAVE THE COST VALUE REDUCED TO 0. THIS IS TO FIX INCORRECT VALUES BEING SHOWN ON THE RETROSPECTIVE STOCK VALUATION REPORT.


Issues Resolved

Works Order Processing

  • Fix to only update WOP multi selection if required.
  • Fix for when viewing the ‘Future Stock Movements’ screen and the user would check or uncheck the ‘Include suggestions from last MRP run’ and the date order would be incorrect.
  • Fix to the ‘Add New Finished Item’ screen opening as blank rather than using the details of the current item in there.
  • Fix to when creating a new works order with operations but the setting ‘Only use Production Lead Time for Works Orders’ and the operations would change the due date for the works order.
  • Fix to not allow parent works order to be backflushed without all child elements being backflushed as well.
  • Fix to make sure the user enters a value for the ‘Appointment Calculation Level’ setting.

Date applied: February 28, 2023