Issues Resolved Important
Important Info

ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v22.1 FOR THE FIRST TIME.  THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.

TRANSACTION HISTORY FOR UNCONFIRMED COSTS WHERE THE NOMINAL HAS NOT BEEN UPDATED WILL HAVE THE COST VALUE REDUCED TO 0. THIS IS TO FIX INCORRECT VALUES BEING SHOWN ON THE RETROSPECTIVE STOCK VALUATION REPORT.


Issues Resolved

Works Order Processing

  • Fix to when allocating a works order to check if the user has ‘Use FIFO Allocations’ setting turned on before using the ‘Auto Allocate Bin’ feature.
  • Fix to calculation of the cost of a works order or estimate that has a sub assembly associated with it and the average buying price is used.
  • Fix to unissuing traceable items where the bin has been deleted and is no longer available to be returned to.
  • Fix for when creating a sub assembly on a works order, the popup to create the sub assembly was appearing multiple times if the user had changed companies multiple times.
  • Fix for when creating a sub assembly during creating a works order, and the user selects a different warehouse, it wasn’t using the warehouse the user selected.
  • The user was allowed to select a deleted operation from a works order on the timesheet entry screen.
  •  Fix to when importing works order lines that are sub assemblies but the setting to not explode BOM’s is turned on to just add the WO line and also set the correct warehouse that gets imported in for these lines.
  • Fix for when allocating a works order and the bin has already been selected.
  • Fix for when allocating works order lines without the user selecting the bin and they are using the ‘Sage SOP Fulfilments’ setting to not select the bin using our FIFO selection process and instead use the Sage one.

Material Resource Planning

  • Amended the ‘Linked Orders’ for MRP warnings to also check the SiconMPPOLine table for any further reasons other than preallcoation where orders could be linked.

Kitting

  • Fix to part building a kit where the components are batch items, now correctly sets the batch amount to be used when building.

Date applied: February 28, 2023