220.0.12
Issues Resolved ImportantImportant Info
ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v22 FOR THE FIRST TIME. THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.
TRANSACTION HISTORY FOR UNCONFIRMED COSTS WHERE THE NOMINAL HAS NOT BEEN UPDATED WILL HAVE THE COST VALUE REDUCED TO 0. THIS IS TO FIX INCORRECT VALUES BEING SHOWN ON THE RETROSPECTIVE STOCK VALUATION REPORT.
Issues Resolved
Works Order Processing
- Fix to set the traceable use by and sell by date when generating the traceable items within the activity. CASE23949
- Fix to ensure the line text is retrieved from the correct works order line.
- Fix to ensure eco batch size form appears for sub assemblies.
- Fix to find the team associated to the labour resource or labour resource group if it cannot be found by the reference.
- Fix to set the sell by and use by date of the traceable adjustment item if it is passed in.
- Fixed object reference error when exploding BOM during Add Stock from Barcoding.
- Fix to stop double eco messages appearing.
- Fix to stop error when converting tuple string to decimal.
- Fix to add UseWarehouseHierarchy override when using the CreateNewWorksOrderLine webAPI method. CASE21634
- Fix to stop error message appearing when cancelling a purchase order with a sub contract line despatched against a deleted works order CASE24331
Material Resource Planning
- Fix to correct the import text for reserved item label template.
- Fix to ignore follow up when clicking select for PO suggestions.
- Fix to show reasons for direct delivery suggested purchase order lines. CASE18926
Date applied: October 10, 2022