211.0.46
Issues Resolved New Features ImportantImportant Info
ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v21.1 FOR THE FIRST TIME. THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.
TRANSACTION HISTORY FOR UNCONFIRMED COSTS WHERE THE NOMINAL HAS NOT BEEN UPDATED WILL HAVE THE COST VALUE REDUCED TO 0. THIS IS TO FIX INCORRECT VALUES BEING SHOWN ON THE RETROSPECTIVE STOCK VALUATION REPORT.
New Features
Material Resource Planning
- New setting added to only create works orders that have been suggested and only if they have been selected. If you create what were the child works orders separately, then they will not be preallocated automatically.
Issues Resolved
Works Order Processing
- Fix to show the correct quantity remaining when receiving the final part of a preallocation that is less than the total of the booked quantity, but this quantity is less than the total preallocated quantity.
Material Resource Planning
- Fix to show the correct purchasing unit of measure and stop showing units that do not have a stock item unit.
Kitting
- Fix to creating a new sales order line that has a kit on without stock. If the user then selects to build the kit this will allocate the new kit to the line and then when the user would save this new line it would get allocated twice incorrectly.