Issues Resolved Important
Important Info

ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v20.1 FOR THE FIRST TIME.  THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.

TRANSACTION HISTORY FOR UNCONFIRMED COSTS WHERE THE NOMINAL HAS NOT BEEN UPDATED WILL HAVE THE COST VALUE REDUCED TO 0. THIS IS TO FIX INCORRECT VALUES BEING SHOWN ON THE RETROSPECTIVE STOCK VALUATION REPORT.


Issues Resolved

Material & Resource Planning

  • Fix to stop removing the warehouse on a suggested purchase order
  • Fix to stop loop when clicking close from suggested purchase orders when clearing out the warehouse from the line (Case 13863)

Works Order Processing

  • Fix to stop timesheets being added, removed or changed when they are for completed works orders and the setting to allow changes to timesheets after completion is disabled.
  • Fix to allow components to unissue when the stock items product group does not maintain history (Case 13429)
  • Fix for nominals to clear up costs when company has changed from unconfirmed costs to confirmed costs (Case 12868)
  • The correct Works Order is now used when trying to despatch using the subcontract management screen

 


Date applied: September 3, 2021