Issues Resolved Important
Important Info

ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v20.1 FOR THE FIRST TIME.  THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.


Issues Resolved

Works Order Processing

  • Fix to showing linked works orders on sales orders where they were not all appearing
  • Fixes to auto creating serial numbers via the works order screen
  • Fix to allowing duplicate batch and serials on a works order finished item
  • Fix to manually adding a works order line that is a sub assembly

Material Planning

  • Fix to requested to date filter for suggested purchase orders
  • Fix to excluding quarantined warehouses when running with warehouse hierarchy
  • Fixed a bug where suggestions were being created for the weekend