Issues Resolved Change in Functionality Important
Important Info

ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v200.0.9 OR HIGHER FOR THE FIRST TIME.  THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.

TRANSACTION HISTORY FOR UNCONFIRMED COSTS WHERE THE NOMINAL HAS NOT BEEN UPDATED WILL HAVE THE COST VALUE REDUCED TO 0. THIS IS TO FIX INCORRECT VALUES BEING SHOWN ON THE RETROSPECTIVE STOCK VALUATION REPORT.


Issues Resolved

Works Order Processing

  • Fix to setting quantities for a sub assembly that is the combination of multiple BOM lines
  • Fix to the works order list infinite scroll problem
  • Fix to put reports in Single Threaded apartment to view activeX controls (reports) when booking-in finished item and receiving a sub contract.
  • Fix to printing reports and labels when receiving sub contract purchase order and booking in the finished item at the same time
  • Fix to set the correct works order number when adding a sub assembly line

Material Planning

  • Leadtime on future stock movements calculates including weekends
  • Fix to calculate calendar days for purchase order on future stock movements and work week for works order lead times
  • Fix to stop follows reasons being deleted when running material planning
  • Fix to deleting follow up reasons to stop incorrect state errors

Kitting

  • Fix to delete only the kit for the sales order line that has been deleted
  • Fix to stop error appearing when attempting to build kits that have been part built
  • Fix to active kits view to no longer store part of the information of the sales order after the preallocation has been deleted
  • Fix to add only a kit for the remainder when changing the line quantity on an existing sales order line

Change in Functionality

Works Order Processing

  • New ‘WIP In Progress Nominal’ report added