ALL USERS MUST BE LOGGED OUT WHEN UPGRADING TO v200.0.9 OR HIGHER FOR THE FIRST TIME.  THIS IS BECAUSE WORKS ORDER FINISHED ITEM TRANSACTIONS WILL BE SWITCH TO BOM BUILD TRANSACTIONS, DUE TO HOW THE SAGE STOCK VALUATION REPORT HANDLES UNCONFIRMED TRANSACTIONS.


Issues Resolved

Material Planning

  • Fix to check the currency has an active period exchange rate set if its not the base or the euro currency when selecting the Suggested Purchase Orders in Material Planning

Works Order Processing

  • Fix to allow Sicon Documents to restrict closing the works order screen based on required document settings
  • Sub contracts can now be viewed after the Works Order has been completed on the Sub Contract Tab

Kitting

  • Fix to keep the Kit even if it cannot allocate all of the lines to the sales order line kit when using the createKitsForSalesOrder WebAPI request
  • Fix to kitting menu item Kit Templates

Date applied: November 30, 2020